Soil Stabilization, Chemical Shoring & Permeation Grouting

Shed Soil Stabilization

Garden Valley, Idaho Sep 25, 2026

Download project slides
Shed with open garage bay during soil-stabilization work
The problem

What we found

On this mountainous property, a 16W × 32L shed was backfilled around large cement barrier blocks with native soil containing organic and other deleterious material; it was not placed in compacted lifts. The shed settled more than 18 inches, damaging its attached roof, plumbing, and electrical.

The solution

How we repaired it

Working with a local general contractor, Polyflow stabilized soil while the contractor mechanically lifted the shed to its original height and supported it. Testing found unconsolidated soil as deep as 12 feet. Polyflow used direct injection at predetermined depths in a grid inside and around the shed after removing its wood floor. The contractor placed temporary hydraulic jacks around the perimeter; Polyflow remained during the lift and added foam where needed to support the jacks. After final injections, the shed, its contents, and attached roof rested on soil stated to be sufficient for their weight.

Explore Soil Stabilization, Chemical Shoring & Permeation Grouting →
The result

What changed

The soil that had decomposed organic matter and that was never compacted properly now has been filled with structural grade high density foam. This foam is designed to last 900 years!

Have a similar problem?

Let us test what is underneath.

We assess the site and test the soil before recommending a repair.

More project experience

Recent case studies

See all projects →
Installing helical tiebacks with a mini excavator
Foundation RepairBoise Foothills, Idaho

Complex Foundation Repairs

A newly developed neighborhood was built on 12 feet to 35 feet of fill material. Over the course of the first few years homeowners experienced differential foundation settlem…

Read the project